Commissioning is where a correctly specified inverter either proves itself or reveals the hidden errors that were built in on site. The goal is a documented, repeatable sequence that confirms safety before power is applied and performance before handover. This checklist is written for EPC engineers and site commissioning teams working with industrial single-phase pure sine wave and modified sine wave inverters, and it follows the logic of IEC 60364 installation practice and IEC 62109 equipment safety.
Documentation and Safety Before Start
• Collect the approved single-line diagram, cable schedule, protection device settings and the inverter datasheet.
• Confirm the assigned DC voltage (12 V, 24 V or 48 V) matches the installed battery bank and wiring.
• Verify that the site risk assessment, isolation points and lock-out procedures are in place.
• Confirm the correct tools, calibrated instruments and personal protective equipment are available.
Pre-Power Mechanical and Wiring Checks
• Inspect the mounting: the enclosure must be level, ventilated and clear of the heatsink airflow path.
• Check all terminal torques against the manufacturer specification.
• Verify that DC and AC cables are separated and that the earth conductor is continuous and bonded.
• Confirm no swarf, tools or loose fasteners remain inside the enclosure.
DC Side Checks
• Measure the open-circuit DC voltage and confirm polarity at the inverter terminals.
• Confirm the battery bank protection fuse or breaker rating is correct for the cable and the inverter input.
• Check that the charge current setting is within the battery maker recommendations.
• With the inverter isolated, confirm there is no leakage or short between positive, negative and earth.
AC Side Checks
• Measure the mains voltage and frequency and confirm they sit inside the inverter acceptance window.
• Verify the output circuit is protected to the correct rating and that downstream loads are isolated for first start.
• Confirm the neutral and earth arrangement matches the installation earthing system.
• Check that the transfer path, whether a bypass or changeover is fitted, operates freely.
First Start-Up Sequence
• Close the DC isolation first and observe the unit power up without alarm.
• Confirm the display and any RS485 communication respond.
• Close the AC output with all loads off and listen for abnormal noise or fan faults.
• Record the start-up log with serial number, firmware version and initial readings.
No-Load Verification
• Measure output voltage and confirm it holds the rated 220-230 V AC at 50 or 60 Hz as selected.
• Check the output waveform on an oscilloscope for a clean pure sine wave where that is specified.
• Confirm standby current is within the datasheet expectation.
• Verify that all indicators and remote signalling report normal status.
Load Testing and Load Sharing
• Apply load in steps, for example 25, 50, 75 and 100 percent of rating, holding each step until readings stabilise.
• Record output voltage, current, frequency and temperature at each step and confirm the derating curve is respected.
• For parallel units, measure the current in each unit and confirm load sharing is balanced and stable.
• Test a surge load, such as a motor start, to confirm the inverter handles inrush without tripping.
• Confirm the battery recharge current returns to normal after the test.
Protection, Alarm and Shutdown Tests
• Simulate a mains failure and confirm the automatic transfer to inverter mode within the specified time.
• Trigger an overtemperature and an overload condition where it is safe to do so, and confirm the alarm and protective shutdown behave as designed.
• Verify short-circuit and reverse-polarity protection by inspection and, where the vendor allows, by a controlled test.
• Confirm the unit restarts correctly after each protective trip.
Common Commissioning Failures to Watch
• Reversed DC polarity, usually caused by a mislabelled battery cable, which can destroy the input stage on first power.
• Undersized DC cable or a loose terminal, which produces voltage drop under load and nuisance low-voltage alarms.
• An earth and neutral fault, where the installation earthing system does not match the inverter neutral arrangement.
• Poor heatsink clearance, which lets the unit overheat only when it reaches rated load in a warm room.
• A charge current setting above the battery maker limit, which shortens battery life and can trip the rectifier.
• Parallel units of different firmware, which leads to unbalanced load sharing and unexplained trips.
Catching these issues during commissioning is far cheaper than finding them after handover, when production or critical operations are already depending on the inverter.
Handover and Records
• Complete the commissioning record with all measured values, test results and any deviations.
• Update the as-built drawings with the actual settings and cable sizes.
• Train the operator on normal start, stop and alarm response.
• Schedule a first review of operating data and a repeat load test for the warranty period.
A disciplined commissioning sequence protects both the equipment and the people who operate it. When every check above is recorded, the inverter handover becomes a verified fact rather than an assumption, and the site gains a baseline for every future service visit.